Our group has accomplished far more than we planned to this
semester by completing over half of the build for our Bailey Alternative High
School Project. We have finished constructing two platforms both 8 feet by 4
feet. We still need to construct the stairs and finish off everything by
painting and adding skirts to the platforms. I personally learned a lot about
how to go about building platforms that are in check with the local code
requirements, and about what it takes to actually put a project like this
together. I also learned a lot from the students of the school on what they
needed for their space. In the spring we plan to finish off the platforms as
well as give the school stairs to access them. Overall we came in ahead of
schedule giving us plenty of time to do the finishing details!